Renovation work on the central section of metro line M3 has begun

Although reconstruction is still in progress in the southern section, with the closure of the metro stations of both Arany János utca and Ferenciek tere on March 7, 2020, the renovation of the central, downtown section of the blue metro line has officially begun.

Scheduled timetable for the reconstruction of the middle section of metro line M3

By closing both Arany János utca and Ferenciek tere metro stations, the reconstruction of the last downtown (middle) section of the so-called blue metro line will begin.

Although the travelling public will first see the changes in traffic on March 9th - as trains are passing through these metro stations without stopping - reconstruction work will begin on March 7th with the official transfer of workspaces and the designation of construction sites.

Actual

Renovation work on the central section of metro line M3 has begun

Although reconstruction is still in progress in the southern section, with the closure of the metro stations of both Arany János utca and Ferenciek tere on March 7, 2020, the renovation of the central, downtown section of the blue metro line has officially begun.

The construction site was demarcated by a fence, and work had begun with the demolition of some station furniture and equipment.

You can browse Monday's photo gallery by clicking HERE and we will keep you updated on the further developments.

Photos: Bence Horváth

Expected changes

As a part of a comprehensive reconstruction on the new line, a modern truck will be built, there will be a complete electrical reconstruction, the safety equipement will be replaced, the train control system and conductor systems will be replaced, the passenger areas and the stations will be renovated​. The renovation of the trains have already started. The first refurbished trains have been in operation since March of 2017. 

 

 

 